Project List >Fabrication, installation and pre-commissioning of 24” oil line riser and tie-in spools. Project title: Fabrication, installation and pre-commissioning of 24” oil line riser and tie-in spools. Location: Abouzar field, Persian gulf Client: Iranian Offshore Oil Company Job summary: Fabrication, installation and installation of a 24” riser pipe as well as relevant tie-in spools in water depth of 38 m Main Job steps include: § Design, engineering and preparation of fabrication and installation documents § Fabrication, hydrotest and anti-corrosion coating of riser and first spool onshore § Installation of riser and first spool offshore § Meteorology and fabrication of second spool offshore § Installation of second spool offshore § Final leak test of the pipeline |
||
|
|
|
|